Home Building Answers Logo
 

Home
Being An Owner Builder
The Contracting Process
The Parts of Your Home
Planning Your New Home
Funding Your Project
Developing Your Budget
Your Building Lot
Plans And Specifications
Cost Estimate
Construction Schedule
The Home Building Sequence
Superintending
Subcontractors
Suppliers
building an energy efficient home
resource links

Click Here for the COOLest house plans on the Internet!!
COOL house plans


Scheduling Your Subcontractors
And Materials Deliveries



Orchestrating the symphony that is home building, the owner builder always has to struggle with the complexities of scheduling construction activities.

This section of our online course in home building for owner builders is where the plan you developed at planning of the construction project is put into action! You have already laid out the sequence of building activities (which activity follows which activity) and determined how long each activity should take to complete.

Here (on this page) we're not talking about planning. We're talking about implementing the plan! And we're going to use the Critical Path Method Diagram (CPM) to illustrate some simple methods of scheduling the day-to-day activities of subcontractors and materials deliveries.

You have done most of the difficult work in scheduling construction when you developed the Critical Path Method Diagram. Now it's a matter of implementing your plan. Again, the purpose of developing the Critical Path Method Diagram was to see how the home goes together sequentially, to see which tasks could overlap, and to be able to visualize it all over time. Now we will see how to use that Critical Path Method Diagram for day-to-day residential construction scheduling.


Using the Critic In Scheduling Construction

Look at the Critical Path Diagram example again. Notice the scale at the top of the diagram with each number representing one day.

Click here for a page of Calendar Strips.

The way you use these is to cut the strips apart and tape them together end-to-end. Next, write a date in each box, starting at the left end with the date you plan to start construction, and placing each succeeding day in the next column to the right. Omit Saturdays and Sundays.

Scheduling With Critical Path Method



The drawing above shows how to use the Critical Path Method Diagram and the Calendar Strips to maintain control of the project. The drawing shows the project starting on January 1. Notice that days 3, 4, 10, 11, 17, 18, 24, 25, and 31 are omitted in January. In this example, these are Saturdays and Sundays.

This doesn't mean that you can't work on weekends. In fact, those two extra days eachweek may be a good time for you to make up time lost to inclement weather or other delays. We just don't use those days for planning purposes. But that's just us. If you want to schedule the work six or seven days a week, be our guest. Finding subcontractors who will work that schedule is another matter!

If you will tape your calendar strip to the wall and put your Critical Path Diagram under it so that the current day's activities coincide with today's date (as shown in the illustration), you can easily tell on what date a future activity should occur.

Hanging a string or a strip of colored paper from the current date will create a Date Line. The Date Line will let you see immediately where you are in the project. Looking ahead you can schedule deliveries and subs for several weeks in advance.

If you lose a day, simply slide the CPM Diagram over. Be sure to advise suppliers and subs of the delay so that people and materials don't start showing up early.

 

Scheduling Strips

A large builder in the Southeast developed his own scheduling construction method. It's a Scheduling Strip. We have included the Scheduling Strip here. When these are cut out and taped together end-to-end, they form a simplified construction schedule. One of these Scheduling Strips is assigned to each home the builder has under construction.

The Scheduling Strips are lined up under a date strip according to where they are in the construction process. By hanging a Date Line from the current date, it is easy for the superintendent to see how to schedule his work on all the houses.

The Scheduling Strip doesn't show some of the relationships revealed in the CPM Diagram, but the superintendent knows the process, and it's enough to keep him on track.

 

electricianScheduling Subs

When you are ready to actually begin construction, you should contact all of your subs and let them know approximately when you will require their services. As the time draws nearer, you can give them a specific date.

If something happens to delay construction, be sure to notify your subs of the delay. One thing you don't want to do is have subs show up before you are ready for them. Once that happens, it tends to be a little harder to get them back when you need them.

 

Scheduling Materials

drywall truckScheduling of materials is a bit easier. Usually two or three days is sufficient time to get a delivery to the job site, unless fabrication is required.

A good example would be trusses, which typically take weeks to fabricate. wWhen pricing materials, find out which items are stock, which are special order, and the lead time for special order items.

Try to make sure the materials are on the job site before the subs arrive. Don't schedule both to arrive the same morning. Your subs will arrive at 7:00, and the materials won't show up until 10:30. You'll have some angry subs on your hands.

If you're expecting framing subs on Tuesday, have the framing materials delivered on Monday. The materials suppliers have to load their trucks and deliver their materials so that they make most efficient use of their equipment. They can't always guarantee delivery at a specified time, like "first thing in the morning."

 


For additional insight to the Scheduling the construction work,
see Lesson Thirteen of our online course
Successful Home Contracting
.



Return to the Contracting Process

bottom-nav home page what does it mean to be an owner builder the contracting process the parts of a home planning the new home project funding your home building project developing a budget for your new home project developing the plans and specifications for your new home developing a cost estimate for your new home developing a construction schedule for your home building project managing the construction process finding and dealing with subcontractors finding and dealing with the materials suppliers for you new home project energy efficiency considerations for your new home links to other resources for your new home project

 

 plans link


copyright

write an article link

link  to this page


Contact Us

 

 

 

 

scheduling construction, residential construction scheduling, home building, owner builder, critical path method
Subs dlck here for information on Home Building Answers' national Subcontractor List write an  article link to this page